Custom LCD RFQ Checklist: What to Send and How to Compare Quotes

Workers at an LCD module assembly line in protective clothing
LCD module assembly line. The sourcing example in this guide is illustrative.
On This Page

What does a supplier need to quote a custom LCD?

A useful custom LCD RFQ identifies what the module must do, where it must fit, what drives it, how it will be verified, and how many units the buyer expects to order. Start with the application, mechanical envelope, host interface, optical and touch requirements, operating conditions, sample quantity, and production forecast. Mark unresolved items as open and ask the supplier to state the assumptions behind its price.

For an OEM buyer, the first goal is a comparable quote. A $9 module and a $12 module may cover different work if one includes a touch controller, optical bonding, and an approved harness while the other covers the bare display. The checklist below gives sourcing and engineering a common way to request, compare, and verify those offers.

1. Define what the supplier will deliver

Name the deliverable in the opening line. A custom segment LCD glass, a TFT module with an FPC, and a bonded display assembly with cover glass and touch are separate purchases. An assembly can also include a driver board, bezel, or tailored packaging. List exactly which parts arrive together and which party supplies or installs the rest.

Ask for a standard option when it can meet the brief

Give the supplier permission to propose a standard module if it fits the available space, host, optical conditions, and supply plan. If only the flex tail or cover lens needs to change, ask for both the stock baseline and the derivative. Compare drawings and acceptance requirements for each option. Tooling, engineering work, and qualification can change even when the visible display area is identical.

If your team is still deciding between a standard module and a derivative, use the display product categories to describe the technology family and share which feature forces customization. A fixed bezel opening may drive a mechanical change, while low-temperature readability may drive a different display or backlight. A short explanation of the constraint is more useful to engineering than a request to customize every attribute.

Use three clear requirement states

Mark each important item Required, Preferred, or Open. For example, a fixed housing window can be required, a neutral black bezel can be preferred, and the cover-glass finish can remain open until samples are compared. An open item needs an owner and a decision date. Otherwise the apparent flexibility can turn into an unplanned drawing change after the quote.

2. Send a drawing that separates fit from visibility

Include an outline drawing with dimensions, units, datums, and a revision identifier. Call out the module outline and active area independently. The active area is the region that produces the image. The visible opening in the enclosure may be smaller or shifted to mask the inactive border. A nominal diagonal tells the supplier very little about either the mounting envelope or the center of the image.

Specify the allowed thickness where it matters. A rear component, solder joint, adhesive, bracket, or bend in the tail can interfere with the enclosure even if the nominal module thickness fits. Show the connector end of the flex in both the flat and installed positions when the installation requires a bend. Include the mating connector part number or its pitch, contact side, and retention style if already selected.

Drawing item What to provide What to verify on the sample
Mechanical envelope Outer width, height, thickness and local keep-outs Assembly fits without force or contact with rear components
Viewing window Active area, visible opening, offset and orientation UI is readable and no required pixels sit behind the bezel
Mounting and stack Datums, brackets, pads, gasket and cover stack No uneven load on the glass or interference with adjacent parts
Flex and connector Exit edge, installed route, length and contact side Cable reaches the board with the required bend and strain relief

For a replacement module, send the old part number with its suffix, clear front and rear photos, the connector markings, and a sound mechanical drawing or physical sample. List any dimensions inferred from a damaged part. Treat those figures as provisional until the replacement drawing is approved. The same connector pitch and pin count can hide important differences in power, pinout, or initialization.

3. Specify the host and software boundary

Identify the processor or display controller, operating system or firmware platform, and native display output. Give the target resolution, color depth, and update pattern if known. If the processor has already been chosen, provide its exact part number and available pins or lanes. A proposed screen should be checked against the real board even when another member of that processor family supports the desired interface.

For a TFT RFQ, ask the supplier to supply the module pinout, timing requirements, power-up sequence, reset behavior, and initialization commands where relevant. Ask who provides the first working implementation and what it covers. Specify whether you expect a datasheet, driver example, evaluation-board configuration, or help reviewing your own board. Ask whether the sample and production module share the same controller and configured interface.

If you are commissioning a custom monochrome segment display, include draft artwork and describe which segments can be active together. Clarify whether the supplier supplies glass only or a driver-equipped module. Confirm polarity, optical mode, backlight needs and electrical drive with the supplier before freezing the layout. See the TFT interface comparison for projects where the display bus is still open.

4. Define the real viewing and installation conditions

Describe where the operator stands, the typical reading distance, who presses the controls, and what the screen must show. A screen carrying large status symbols at arm’s length has a different brief from a display carrying a dense graph or small alarm text across a cabinet aisle. Send representative artwork or a mock interface if available. Contrast and font weight can change what the operator can read even when the panel specification stays the same.

Ask the supplier to state whether a brightness figure is typical or minimum, how and where it is measured, and what the optical stack includes. If the product will be used outdoors, include the light direction, cabinet angle, target ambient conditions, and any planned shade. Ask for installed-stack comparisons if you are weighing stronger backlighting against a different cover or optical bonding. The outdoor HMI guide explains how to frame that test.

Record the temperature range in two parts. Operating conditions describe when the product must show and accept input. Storage conditions describe a non-operating exposure and the expected recovery afterward. Give any known moisture, vibration, cleaning chemistry, shock, or EMC conditions and state who will test the assembled product. A module specification alone cannot demonstrate a sealing or system-level compliance claim.

Define touch as a use case

State whether the operator uses bare hands, gloves, or a stylus. If gloves are required, give samples, thickness, or the material. Describe surface moisture and the difference between detecting a finger while wet and ignoring water droplets. List the desired cover material and thickness, touch interface, mounting stack, and host platform if known. Ask which settings need tuning and whether the prototype can be tested with the production enclosure, grounding arrangement, and power supply.

5. Give the supplier quantities and milestones it can price

State how many units you need for bench evaluation, pilot assembly, and the first production purchase. Give estimated annual demand and an order cadence as estimates when appropriate. A price based on one annual purchase may differ from a program based on small releases over the year. Ask whether quoted minimums apply per part number, variant, shipment, or production batch.

Tell the supplier which date matters. A prototype may need to arrive for integration, while the first production lot has a separate delivery deadline. Ask the quote to identify the event that starts each lead time, such as payment, drawing approval, tooling release, or component allocation. Request the quantity tier, currency, delivery basis, commercial term, and validity period for each option. Record assumptions so you can update offers when the buyer’s forecast or design changes.

Compare the costs on the same scope

Ask suppliers to break out the sample and evaluation kit, tooling or non-recurring engineering, production unit price at the same volume levels, required accessories, and packaging. If tooling is included in the price, ask where it is recovered and what happens if lifetime demand falls below that assumption. Confirm tooling ownership, storage conditions, and any charges for repeat samples or drawing revisions before approval.

For example, suppose one hypothetical supplier quotes $9.40 per module plus $1.70 for the required cover and touch assembly, and another quotes an assembled unit at $10.60. The comparable unit prices are $11.10 and $10.60 before one-time charges, freight, and any other costs. The second quote is only lower for a given batch if the overall scope and additional charges support that comparison. These figures illustrate a calculation and are neither Sunovi prices nor market benchmarks.

6. Plan sample approval and shipment inspection

Ask for a sample list that identifies the module, drawing revision, firmware or initialization package, accessories, and any deliberate differences from production. Keep one accepted unit as a physical reference when it is useful. Pair it with a written list of acceptance criteria so a later comparison does not depend on memory, a phone photo, or different viewing conditions.

Use the sample to test the whole assembly

Start with the board on the bench, then install the sample using the intended bracket and cable routing. Check connector insertion and strain relief before power-up. Verify reset and image orientation, full-screen test patterns, any known touch interactions, and readable UI in the intended lighting. If the device needs to start cold or display continuously in a hot enclosure, include those use cases and agree on pass criteria with the supplier. Record the build state, failure conditions, and next owner for each issue.

For factory testing, write down which checks the supplier performs on every unit and which require sampling or qualification. Separate routine functional checks from tests that take time or may be destructive. A shipment inspection can cover part and revision labels, quantities, outer carton condition, antistatic packaging where required, connector or glass protection, and the agreed visual and functional sampling. Give the supplier the same criteria your receiving team will use. IEC 61340-5-3 is a reference for the properties of packaging for electrostatic-discharge-sensitive devices. Its applicability and packaging configuration should match the product. IEC packaging standard.

Keep the approved revision traceable

Ask how the approved drawing number, part suffix, lot identifier, firmware revision, and packaging specification appear on the order or shipment paperwork. Agree how the supplier will notify you of changes that could affect fit, electrical compatibility, appearance, or reliability. If you depend on a particular controller or backlight configuration, define which changes need review and which can be handled under the agreed specification.

Keep the supplier's quote and the revision package linked when you issue a pilot purchase order. For example, if the drawing changes only the flex exit, revisit the mating connector, installation clearance, and any fixture that holds the module during testing. Check whether that change also alters tooling or the lead-time trigger. This avoids carrying a price or delivery assumption from an earlier configuration into the order for the new one.

Worked example for an industrial controller retrofit

An illustrative buyer needs a 4.3-inch display for a line controller with a fixed cutout. The original purchase description gives only the diagonal. The controller uses a fixed processor board, and a hard bezel limits both the visible window and the route of the cable. Operators mostly read warnings and numbers under workshop lighting. The buyer expects 12 evaluation samples, 150 pilot units, and about 1,200 units in a typical year, subject to demand.

The revised RFQ includes a photograph of the installed panel, the old part suffix, a drawing with the connector location, and the host’s available display outputs. It asks suppliers to quote any candidate that fits without a board respin and to disclose where an adapter or firmware change is needed. On incoming samples, the buyer verifies window alignment, connector access, ability to read the alarm states from the intended viewing position, and a repeated cold power cycle. This example illustrates a sourcing workflow. It is not a reported Sunovi project or a production acceptance result.

Copy this short RFQ checklist

  1. State the application and whether the project is a new design or a replacement.
  2. Define the deliverable and the included display, touch, cover, cable, and accessories.
  3. Attach a revised drawing with the mechanical envelope, active area, orientation, mounting limits, and flex route.
  4. Give the host, available interface, known timing or resolution, and required software deliverables.
  5. Describe lighting, viewing position, touch use, temperature, and other environmental needs.
  6. Give sample, pilot, first-order, and expected annual quantities with target dates.
  7. Ask for itemized pricing, minimums, tooling terms, lead-time triggers, and assumptions.
  8. Define the sample approval, manufacturing release, packaging, and shipment inspection deliverables.

Frequently asked questions

Can I request a quote without a drawing?

Yes. Send a sketch, the target window or envelope, the application, host, and quantity expectations. Request an indicative price and a list of open assumptions. Before placing a custom production order, agree a module drawing with revision control and resolve any features that determine fit or tooling.

Is a minimum order quantity the same as a production batch size?

The minimum order quantity is a commercial commitment. Production batch size is how the supplier plans to make units. A supplier may make a larger batch or impose different minimums for alternate variants or reorders. Ask how the minimum applies to ordering, scheduled releases, and any inventory the supplier holds.

Should I request an evaluation kit?

Ask for a kit if you need an adapter, suitable power source, harness, or known boot configuration to make the sample usable. Check what the kit can demonstrate, then repeat the relevant tests on your own board and enclosure before approving production.

What if two offers use the same controller and resolution?

Compare the exact revision package. Modules with the same display controller can differ in pinout, power sequencing, initialization settings, dimensions, backlight, and cover construction. Use the approved drawing and a functional test on the intended host to establish compatibility.

How do I share drawings that contain confidential information?

Begin with a non-confidential summary and offer a redacted outline if it is sufficient for screening. Agree on an approved sharing method before sending restricted files. Keep revision details and acceptance information in the controlled package passed between your engineering and sourcing teams.

Conclusion

A custom LCD quote is most useful when it describes a complete, testable configuration and the commercial terms for that configuration. Send the mechanical and electrical limits early, define where the display will be used, and ask each supplier to state the same costs and approval steps. After evaluation, link the approved sample to the drawing, firmware, and packaging requirements so your first production order and shipment inspection refer to the same product.

Privacy